Broadway Subway Project Broadway Subway Project
Skip to navigation Skip to Contents Skip to Accessibility Statement
Home Construction Current Work

We are currently focused on completing the station structures and interiors, installing the SkyTrain tracks and systems to run the trains, and rebuilding the streets above the new underground stations. We provide regular updates about construction to email subscribers, on social media, and here on our website. Please see notifications below and contact us if you have any questions.

You can access businesses, services and residences on Broadway throughout construction. Check our maps page for up-to-date parking and access maps of all Broadway stations.

Visit our Construction Timeline for more information.

Notices

4 lanes open and south sidewalk connected in Mount Pleasant

  • On June 25, 2026, E. Broadway between Quebec and Main streets opened to 4 lanes.
  • The sidewalk on the south side of Broadway was also reconnected.
  • Crews continue to construct the final streetscape.
  • Businesses and services remain open and accessible throughout the work.

General Information

Great Northern Way-Emily Carr Station

  • Great Northern Way-Emily Carr hours of work: 6 a.m. to 10 p.m. Intermittent night work.  
  • Elevated guideway typical hours of work: 6 a.m. to 10 p.m. Intermittent night work.
  • Dynamic testing is underway on the elevated guideway. You may see SkyTrain vehicles moving along the guideway to test systems and the new track.
  • Crews are building the new station, including concrete and rebar activities and installation of mechanical, electrical and plumbing systems, with increased deliveries of supplies.
  • Crews are backfilling the station to fill the space between the underground station roof and the road above.

Mount Pleasant Station

  • Typical hours of work: 6 a.m. until 10 p.m. Trucks may arrive on site as early as 5 a.m. Intermittent night work.
  • Crews are building and fitting out the station, including installing mechanical, electrical, plumbing systems. Deliveries of construction materials and equipment continue.
  • On June 25, 2026, E. Broadway between Quebec and Main streets opened to 4 lanes.  
  • The sidewalk on the south side of Broadway was also reconnected.
  • Crews continue to construct the final streetscape.
  • Businesses and services remain open and accessible throughout the work.

Broadway-City Hall Station

  • Typical hours of work: 6 a.m. until 10 p.m. Intermittent night work.
  • Crews are building the new station, including concrete and rebar activities and installation of mechanical, electrical and plumbing systems, with increased deliveries of supplies.
  • Crews are backfilling the station between Alberta and Cambie streets to fill the space between the underground station roof and the road above.
  • Lane reductions on Cambie Street due to construction of the Canada Line/Millennium Line underground connections.

Oak-VGH Station

  • Typical hours of work: 6 a.m. to 10 p.m.
  • Crews are building and fitting out the station, including concrete and rebar activities and installing mechanical, electrical, plumbing systems, with increased deliveries of supplies.
  • Crews are removing the traffic deck and backfilling the station. W. Broadway is reduced to one lane in each direction during traffic deck removal and road reconstruction work.
  • Permanent utility relocation work is ongoing at Laurel Street.

South Granville Station

  • Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
  • Crews are building and fitting out the station, including concrete and rebar activities and installing mechanical, electrical, plumbing systems, with increased deliveries of supplies.
  • Permanent utility relocation work ongoing on Hemlock Street and in the laneway south of W. Broadway with intermittent lane closures.

Arbutus Station

  • Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
  • Crews are building and fitting out the station, including concrete and rebar activities and installing mechanical, electrical, plumbing systems, with increased deliveries of supplies.
  • W. Broadway reduced to one lane in each direction between Burrard and Arbutus streets to support construction activities including traffic deck removal and backfilling.
  • Permanent utility relocation work is ongoing at Arbutus Street.

Tunnels

  • Hours of work: up to 24/7 for work inside tunnels
  • Crews are installing the SkyTrain track, crew walkway, and systems to complete tunnel fit out.

Construction Notice Archive