We are currently focused on completing the station structures and interiors, installing the SkyTrain tracks and systems to run the trains, and rebuilding the streets above the new underground stations. We provide regular updates about construction to email subscribers, on social media, and here on our website. Please see notifications below and contact us if you have any questions.
You can access businesses, services and residences on Broadway throughout construction. Check our maps page for up-to-date parking and access maps of all Broadway stations.
Temporary vehicle closure of Broadway at Main Street in effect
One block of E. Broadway between Main and Quebec streets is closed to vehicles for approximately 4 months.
Sidewalks on E. Broadway will remain open. Residences, businesses and services will remain open and accessible.
All 44 traffic deck panels and supporting girders have been removed. Crews are completing utility relocations, backfilling, and rebuilding the road above Mount Pleasant Station.
Click on the options below to see more information or view maps showing the traffic changes.
Starting at 7 a.m. on Monday, January 26, the block of E. Broadway between Main and Quebec streets will be closed to all vehicle traffic for approximately four months.
During this time, buses and local traffic will be detoured around the one-block closure using E. 8th Avenue.
Sidewalks will remain open on E. Broadway and access to businesses, services and residences will be maintained at all times.
Work hours: 7 a.m. to 10 p.m., Monday through Saturday. There may be occasional finishing work onsite after 10 p.m., work on Sundays or on holidays.
Crews will remove the traffic deck panels and supporting girders. Activities include, but are not limited to, backfilling, road repairs, crane activities, saw cutting, welding, as and when needed landscaping and occasional hydro vac.
The map below shows temporary traffic changes that will be in effect for approximately four months starting January 26. (click here to view a larger version)
Over the next three months, crews will focus on waterproofing, concrete pours, rebar work, and backfilling around the station entrance and the area where tracks transition from elevated to tunnels.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
When overnight work is required, work hours can range from 10 p.m. to 5 a.m.
Temporary traffic changes related to the delivery of materials, road repairs, equipment movement and concrete pours.
Over the last few months, crews have completed a major milestone: track installation is now fully connected from VCC–Clark Station through to Broadway–City Hall Station.
Work at the elevated guideway will continue through the fall as rail is welded and pulled into the remaining tunnels all the way to Arbutus Station.
Regular hours on the elevated guideway are from 6 a.m. to 9 p.m.
You may experience some elevated noise during specific activities.
Mount Pleasant Station
Typical hours of work: 6 a.m. until 10 p.m. Trucks may arrive on site as early as 5 a.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
All 44 traffic deck panels and supporting girders have been removed. Crews are completing utility relocations, backfilling, and rebuilding the road above Mount Pleasant Station.
One block of E. Broadway between Main and Quebec streets is closed to vehicles for approximately 4 months starting January 26
Utility investigations on Main Street at Broadway will begin as early as February 25.
This work is required in preparation for the reinstatement of permanent utilities in the area and marks the next stage of construction for the future Mount Pleasant station.
Regular work hours are from 6 a.m. to 10 p.m.
Work activities include but are not limited to: investigating the existing utilities, saw cutting, hydrovac excavation, road work and backfilling.
Work to complete Mount Pleasant Station continues as traffic deck removal and road reconstruction gets underway this winter.
Beginning January 26, E. Broadway will be closed to vehicle traffic between Main and Quebec streets for approximately four months, while crews complete traffic deck removal, utility relocation and road reconstruction work in that block.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
When overnight work is required, work hours can range from 10 p.m. to 6 a.m.
Starting at 7 a.m. on Monday, January 26, the block of E. Broadway between Main and Quebec streets will be closed to all vehicle traffic for approximately four months.
During this time, buses and local traffic will be detoured around the one-block closure using E. 8th Avenue.
Sidewalks will remain open on E. Broadway and access to businesses, services and residences will be maintained at all times.
Work hours: 7 a.m. to 10 p.m., Monday through Saturday. There may be occasional finishing work onsite after 10 p.m., work on Sundays or on holidays.
Crews will remove the traffic deck panels and supporting girders. Activities include, but are not limited to, backfilling, road repairs, crane activities, saw cutting, welding, as and when needed landscaping and occasional hydro vac.
Over the next three months, crews will focus on waterproofing, concrete pours, and rebar work to construct the station and connect to the existing Canada Line.
Backfilling work will continue and move west towards Cambie Street, and backfilling will begin on Cambie Street this spring, followed by street restoration.
Utility work will take place on Yukon Street and W. Broadway west of Alberta Street.
Additionally, micropiling work will take place this spring on W. Broadway between Yukon and Cambie streets.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
When overnight work is required, work hours can range from 10 p.m. to 6 a.m.
Expect temporary traffic changes related to the delivery of materials and construction activities.
Crews will continue installing permanent storm and sanitary utilities on Yukon Street between W. 8th and Broadway through April and into additional phases through the spring on Yukon Street south of Broadway, and Broadway west of Alberta Street.
Beginning March 23, Yukon Street will be closed at Broadway. Access will be maintained via 8th Avenue for local traffic and laneway access, including commercial vehicles and residential parking.
Regular work hours are Monday to Saturday from 7 a.m. to 5 p.m. There may be occasional work past 5 p.m., overnight, and on Sundays and holidays. If overnight work is required, work hours can range from 10 p.m. to 6 a.m.
Work at the future Broadway-City Hall Station is progressing, and in the coming months crews will continue installing permanent storm and sanitary utilities in the area. This work will be completed in phases and is expected to continue through the spring.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
Some activities, such as tie-ins to existing utilities, or installing temporary bypasses, may require overnight work between 10 p.m. and 6 a.m.
Traffic will not be permitted northbound on Yukon Street between W. 8th Avenue and W. Broadway.
Oak-VGH Station
Typical hours of work: 6 a.m. to 10 p.m.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Crews are backfilling the station at Laurel Street to fill the space between the underground station roof and the road above.
Permanent utility relocation work is ongoing at Laurel Street.
Crews have started backfilling between Laurel and Oak streets, gradually restoring the space above the station roof and completing installation of permanent utilities near the station.
Inside the station, masonry works, mechanical and electrical installation continues. As activity increases, the neighbourhood will see more trucks, equipment, and crews on site, along with some noise and temporary traffic changes.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
When overnight work is required, work hours can range from 10 p.m. to 6 a.m.
Work on the future Oak-VGH station is progressing and crews will begin reinstating permanent utilities in the area as soon as the end of November. Utility work is expected to be completed through spring 2026.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
If overnight work is required, work hours can range from 10 p.m. to 6 a.m.
Regular temporary lane closures on W. Broadway between Oak and Laurel streets between 7 a.m. and 7 p.m., overnight or on weekends may be implemented to support construction activities and deliveries.
South Granville Station
Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Permanent utility relocation work ongoing on Hemlock Street and W. Broadway with intermittent lane closures.
This winter, crews are reinstating permanent utilities in and around the station.
Regular hours of work are from Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work that starts earlier or work on Sunday and holidays.
Regular temporary lane closures on W. Broadway on weekdays between 7 a.m. and 5 p.m., overnight or on weekends to support construction activities.
Station construction is expected to continue through 2026.
Permanent utility work at the future South Granville Station is expected to begin in late November now that preparatory bypass activities have been completed.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
When overnight work is required, work hours can range from 10 p.m. to 6 a.m.
Temporary lane closures and changes to pedestrian access to accommodate the reinstatement of utility pipes and equipment staging.
Arbutus Station
Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
W. Broadway reduced to one lane in each direction between Burrard and Arbutus streets to support construction activities.
Construction at the future Arbutus Station is entering a new phase, with crews beginning to reinstate permanent utilities and remove the traffic deck.
One lane in each direction will be maintained on W. Broadway as crews rebuild the roadway above the completed station roof.
Work to install permanent utilities will begin in spring between Arbutus and Cypress streets.
Regular hours of work are from Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work that starts earlier or work on Sunday and holidays.
Crews will continue the construction of the future Arbutus Station. This work includes rebar installation, carpentry and related activities mostly inside the station
Regular work hours continue through the day and night hours proceed from 10 p.m. to 6 a.m.
Some intermittent elevated noise related to construction activities.
Temporary traffic changes may be in place during some construction activities.